Case Study: Murphys – Road Surfacing Works to Provide Access Points and Utility Trenches
Project Overview
This case study highlights the challenges and successful implementation of road surfacing works designed to provide access points and utility trenches for a large-scale urban development project. The primary objective of the project was to create safe, durable, and accessible routes for construction vehicles and workers while ensuring that utility services could be efficiently installed and maintained.
Client Overview
J Murphy and Sons are installing heavy duty HV cables from an offshore windfarm at Happisburgh to Necton Power Station. The project required tarmac access points to be installed at numerous points along the 76 mile route as well as the reinstatement of road crossings. Temporary access routes were needed to allow for the installation of these utilities and provide continued access for site operations throughout the construction phase.
Challenges
Several challenges were encountered during the planning and execution of this road surfacing and trenching project:
Objectives
The objectives for the road surfacing works were:
Methodology
Implementation
The project was executed in a phased manner to ensure that each access point and trench was completed without disrupting the overall timeline. The construction team used modern machinery to carry out trenching and road preparation work efficiently. Road surfacing was completed in stages, starting with the primary access routes, followed by secondary roads and utility trenches.
The installation of utilities was synchronized with the surfacing of the roads to ensure minimal disruption. Trenches were backfilled after the utilities were laid, and the road surfacing was completed promptly afterward. Safety measures, including temporary signage and barriers, were put in place to protect workers and the public at all times.
Results
Conclusion
The road surfacing and utility trenching project was a success due to careful planning, effective execution, and ongoing collaboration with local authorities and utility providers. The access points provided critical support for the ongoing project and ensured that construction operations proceeded without significant disruption to the surrounding area. The lessons learned from this case will help inform future road surfacing projects, particularly in urban environments where constraints and risks must be carefully managed.
MW Surfacing Limited are leading experts for all commercial and domestic surfacing work in Norfolk & East Anglia